10 · Project — Scaled Program Delivery Plan

This project combines every Level 3 module into one deliverable: a delivery plan for a program spanning multiple teams, the way a Release Train Engineer, program manager, or senior Scrum Master would build one.

The scenario

Three teams (Checkout, Catalog, and Platform — 5 people each) are jointly delivering a new marketplace feature launching in 12 weeks. Checkout and Catalog depend on a shared API that Platform owns. The client is overseas and works 6 timezone hours ahead. The organization already runs CI/CD and wants the launch delivered without a code freeze.

Step 1: Scaling framework choice (Module 01)

A lightweight Scrum-of-Scrums model is chosen over full SAFe: three teams is below the threshold where SAFe's overhead pays for itself, but informal coordination alone won't catch cross-team dependencies at this scope.

Step 2: Distributed-team working agreement (Module 02)

Practice Decision
Overlap window 2 hours of daily overlap, used for the shared Scrum of Scrums plus any live pairing
Async default Refinement and design docs written async first; sync time reserved for decisions, not information transfer
Documentation Every cross-team API decision recorded in a shared doc within the overlap window, not left to chat history

Step 3: Delivery model (Module 03)

Feature work stays fully Scrum inside each team; the shared Platform API is delivered Kanban-style with a class-of-service lane for "blocking another team," which jumps the Platform backlog ahead of Platform's own internal priorities.

Step 4: Cross-SDLC risk register (Module 04)

Risk Phase Mitigation
Shared API contract changes after Checkout/Catalog build against it Design API contract frozen and versioned before either dependent team starts integration
No code freeze, but a launch date is fixed Release Feature-flag every launch item; toggle off anything not ready by launch day
Overseas client feedback loop too slow for weekly iteration Requirements Client reviews a recorded walkthrough async, plus one live session per overlap window weekly

Step 5: CI/CD integration (Module 05)

Each team ships to a shared staging environment behind feature flags on every merge; a nightly integration test suite runs across all three teams' services so cross-team breakage surfaces the next morning, not at launch-week integration.

Step 6: Stakeholder metrics (Module 06)

Metric Audience Cadence
Cross-team dependency burn-down Program stakeholders Weekly
Feature-flag readiness (% of launch scope toggle-ready) Client + leadership Bi-weekly
Cycle time on the Platform "blocking" lane Program stakeholders Weekly

Step 7: Dependency management (Module 07)

A shared dependency board tags every Checkout/Catalog story that needs the Platform API, reviewed at a twice-weekly, 15-minute Scrum of Scrums capped to cross-team blockers only.

Step 8: Contract structure (Module 08)

The overseas client relationship runs on a T&M-with-cap model with a "money for nothing" clause, so the fixed 12-week program budget can absorb the client reprioritizing which non-launch-critical features ship in the final two weeks.

Step 9: Technical debt guardrail (Module 09)

Given the no-freeze, feature-flagged approach, the program reserves 10% of each team's sprint capacity for debt incurred by flag scaffolding, with an explicit backlog item to remove dead flags within two sprints of launch.

How It Actually Works

This plan's nine decisions aren't independent choices bolted together — each one is compensating for a specific failure mode that a different one of this plan's own decisions would otherwise create, and seeing those cross-links is what separates a coherent program plan from a checklist of separately-good ideas.

Why the class-of-service lane for Platform is what actually makes the Scrum-of-Scrums choice viable. Choosing lightweight coordination over SAFe (Step 1) only works if the shared Platform dependency doesn't become an unmanaged bottleneck — three teams below SAFe's overhead threshold (Module 01) still concentrate all cross-team risk onto one team's backlog the moment two other teams depend on it. The "blocking another team" class-of-service lane is the specific mechanism that prevents Platform's own internal priorities from silently starving Checkout and Catalog — without it, the lightweight coordination choice from Step 1 would be undermined by exactly the kind of invisible dependency Module 07 describes.

Why freezing the API contract before feature flags exist is a strict prerequisite, not a parallel workstream. Feature-flagging launch items (Step 4's release risk) only de-risks the release date — it does nothing about the design-phase risk that Checkout and Catalog are building against a contract that might still change. If the API froze after both teams started integrating, every subsequent change would ripple through both teams' already-built code (the big-bang-integration mechanism from Module 02, Level 1), regardless of how good the feature-flag and no-freeze release strategy is. This is why the plan sequences it as an early Design-phase gate before either dependent team starts — the two risk mitigations target different SDLC phases (Module 04) and neither substitutes for the other.

Why the nightly cross-team integration suite has to exist alongside feature flags, not instead of them. Feature flags decouple deployment from user exposure (Module 05) but say nothing about whether three teams' services actually compose correctly when merged — that's a technical integration question, not a release-sequencing one. Running the suite nightly rather than only at launch-week is applying the same short-feedback- loop principle from Module 01, Level 1 one level up: a compatibility break found the morning after it's introduced costs one day's rework; the same break found during launch week, after weeks of further work built on the broken assumption, costs the entire program's remaining schedule.

Why the debt-scaffolding guardrail is aimed specifically at flags, not debt in general. A no-freeze, feature-flagged approach necessarily accumulates a specific, predictable kind of debt — dead flags and their branching logic — that ordinary Boy-Scout cleanup (Module 09) won't naturally catch, because a dormant flag doesn't get touched by future feature work the way the checkout-module example's hardcoded coupling did. Reserving capacity with an explicit removal deadline compensates for the one place this program's chosen delivery style creates debt that its own normal maintenance cycle wouldn't otherwise surface.

Program deliverable — what to produce

For a multi-team program of your own choosing, produce:

  1. A scaling-framework decision (lightweight Scrum-of-Scrums, SAFe, or another) with one sentence justifying the choice against team count and dependency density.
  2. A distributed-team working agreement covering overlap hours and the async/sync split.
  3. A 3-item cross-SDLC risk register spanning at least two different SDLC phases.
  4. A CI/CD integration plan describing how cross-team breakage is caught before launch, not during it.
  5. A 3-metric stakeholder reporting cadence.
  6. A dependency-visibility mechanism plus its meeting cadence.
  7. A contract-model decision for any external party, using the Module 08 framework.
  8. One technical-debt guardrail specific to the delivery approach chosen.