04 · Scheduling Basics

Once scope is broken down into work packages (Module 3), the next question is: in what order, and by when? Scheduling turns a list of work into a time-bound plan by sequencing tasks, estimating durations, identifying dependencies between them, and surfacing the critical path — the sequence of tasks that determines the earliest the whole project can finish. This module covers the foundational tools: Gantt charts, task dependencies, and a first pass at critical path thinking (a full treatment, including resource leveling, is in Level 2).

From WBS to schedule: durations and dependencies

Each work package from the WBS needs two things before it can be placed on a timeline: an estimated duration (how long it takes) and its dependencies (what has to happen before it can start, and what's waiting on it to finish). There are four standard dependency types:

Dependency type Meaning Example
Finish-to-Start (FS) Task B can't start until Task A finishes Can't paint a wall until drywall is up
Start-to-Start (SS) Task B can't start until Task A starts QA test-writing can start once development starts
Finish-to-Finish (FF) Task B can't finish until Task A finishes Final proofreading can't finish until final edits finish
Start-to-Finish (SF) Task B can't finish until Task A starts Rare — e.g., old system can't be shut down until new system starts running

Finish-to-Start is by far the most common dependency in everyday project schedules; the other three matter mainly when work genuinely overlaps.

Gantt charts

A Gantt chart is the standard visual for a project schedule: each task is a horizontal bar, positioned along a timeline, with its length showing duration and its position showing when it starts and ends. Dependencies are usually shown as arrows connecting the end of one bar to the start of another.

A simplified Gantt chart for a small product launch, shown as a table (each represents roughly one week):

Task Wk1 Wk2 Wk3 Wk4 Wk5 Wk6
Finalize requirements
Design
Development
Testing
Launch prep

Reading this: Development can't start until Design has produced enough to build against (an FS or SS dependency), Testing overlaps the tail end of Development (an SS dependency, since some testing can begin on completed pieces before all development finishes), and Launch prep is the final task, dependent on Testing finishing. The chart makes the whole sequence — and where things overlap versus wait — visible at a glance, which is exactly why it remains the default view in almost every scheduling tool covered in Module 9.

Critical path: the sequence that sets your finish date

Not every task delay pushes out the project's end date — only delays to tasks on the critical path do. The critical path is the longest sequence of dependent tasks from start to finish; it determines the shortest possible time the project can take. Tasks not on the critical path have float (also called slack) — some amount of time they can slip without affecting the finish date.

Take a small example with four tasks and their durations and dependencies:

Task Duration Depends on
A — Requirements 3 days
B — Design 5 days A
C — Content writing 2 days A
D — Development 4 days B
E — Launch 1 day C, D

There are two paths from start to finish:

  • A → B → D → E: 3 + 5 + 4 + 1 = 13 days
  • A → C → E: 3 + 2 + 1 = 6 days

The longest path, A → B → D → E at 13 days, is the critical path — this is the true minimum project duration. Task C (Content writing) has 13 − 6 = 7 days of float: it could take up to 7 extra days without pushing the launch date out, because it's not on the path that determines the finish. But if Task B (Design) slips by even one day, the whole project slips by one day, because it sits directly on the critical path. This is why an experienced PM doesn't chase every yellow flag equally — they watch the critical path far more closely than tasks sitting on slack. A full method for calculating float mathematically (the Critical Path Method, with forward and backward passes) is covered in Level 2, Module 2; this module's goal is the concept: know which tasks actually control your finish date.

A worked example: a schedule that looked fine until the critical path shifted

A team is building a mobile app feature with four work packages: API design (2 days), backend build (6 days, depends on API design), UI design (3 days, no dependency — can start immediately), and front-end build (5 days, depends on both backend build and UI design being far enough along). At the project kickoff, the PM eyeballs the schedule and assumes the backend build — the longest single task — is the thing to watch.

Running the two paths: API design → backend build → front-end build = 2 + 6 + 5 = 13 days. UI design → front-end build = 3 + 5 = 8 days. The critical path is the first one, through backend build, confirming the PM's instinct — for now. Two weeks in, backend build finishes a day early (5 days instead of 6), but UI design — which had 13 − 8 = 5 days of float — slips by 6 days due to a designer being pulled onto a different fire. The UI design path is now 3 + 6 = 9 days late-start-adjusted, versus the backend path's 2 + 5 = 7 days: the critical path has shifted to run through UI design. A PM who kept watching only the backend build (their original assumption) would have missed this until front-end build was blocked waiting on a UI design that was quietly eating all its float. The lesson: the critical path isn't fixed at kickoff — it has to be re-evaluated any time a task's actual progress deviates from plan.

How It Actually Works

A dependency network is formally a directed acyclic graph (DAG): each task is a node, each dependency is a directed edge, and "acyclic" is not optional — if Task B depends on Task A and Task A (even transitively) depends on Task B, no valid schedule exists at all, and scheduling software will throw a circular-dependency error rather than silently computing a wrong date. Finding the finish date is a topological sort followed by a single forward pass: process nodes only after all their predecessors are processed, tracking finish[node] = max(finish[predecessor] for predecessor in dependencies) + duration. This is why adding a single dependency between two previously-parallel tasks can suddenly change the project end date even though no task's own duration changed — you've merged two independent paths through the graph into one, and the new critical path is max() of the two former paths rather than the shorter of the two running in parallel. A Gantt chart is just a visual rendering of this graph's forward-pass solution laid against a calendar axis; the bars' positions are computed, not drawn by judgment. (Level 2's Advanced Scheduling module runs the full forward and backward pass to get float, not just the finish date.)

Exercise

Using the four-task example structure above (a small set of dependent tasks), sketch your own five-task schedule for a project of your choice — list each task, its estimated duration, and what it depends on. Identify every path from start to finish, calculate each path's total duration, and name the critical path. Then pick one non-critical task and state how much float it has, and one critical task and explain, in a sentence, what would happen to the finish date if it slipped by three days.