10 · Project — Program Plan for 3 Related Projects

This is the Level 3 capstone project: build a full program plan for three related projects, applying every module in this level — benefits mapping, dependency sequencing, quantified risk, vendor terms, PMO-style rollup reporting, and EVM-based forecasting — as one worked deliverable rather than ten separate exercises.

The scenario

A mid-size retailer is launching a loyalty program. It requires three related projects:

  1. Loyalty platform build — the core points/rewards engine (internal team, 12 weeks, 8 engineers).
  2. POS integration — connecting in-store checkout systems to the loyalty platform (a vendor contract, fixed-price, 8 weeks).
  3. Marketing launch campaign — customer acquisition and app onboarding (internal team, 6 weeks, 4 people, cannot start until the platform is feature-complete).

Step 1 — Benefits map

Benefit Target Owner Contributing projects
Increase repeat purchase rate +8 percentage points within 2 quarters of launch VP Marketing Loyalty platform, Marketing launch
Reduce checkout friction for enrolled members Under 5 extra seconds at POS Head of Retail Ops POS integration
Grow email-marketable customer base +50,000 opted-in customers VP Marketing Marketing launch

Step 2 — Dependency map and sequencing

From To Dependency Type Slack
Loyalty platform build POS integration Points API must be live for integration testing Finish-to-start (partial — API portion only) 1 week
Loyalty platform build Marketing launch Platform must be feature-complete before campaign can promise real rewards Finish-to-start 0 weeks (critical)
POS integration Marketing launch In-store enrollment must work before in-store campaign push Finish-to-start 2 weeks

Sequencing across a 12-engineer combined internal capacity cap (8 platform + 4 marketing, POS integration is vendor-staffed and doesn't compete for internal capacity):

Weeks Active work
1–10 Loyalty platform build (8 engineers)
9–16 POS integration (vendor team, starts once points API is live at week 9, per the 1-week-slack dependency)
11–16 Marketing launch prep (4 people) — starts once platform is feature-complete (week 11, one week after week-10 completion accounts for a short buffer), runs in parallel with the tail of POS integration since campaign prep doesn't need POS finished, only the platform
17–22 Marketing launch execution — starts after POS integration completes (week 16) plus 1 week transition, respecting the 2-week-slack dependency

Step 3 — Quantified risk register (program level)

ID Risk Probability Impact EMV Response
R1 POS vendor's fixed-price estimate was based on incomplete store hardware inventory 35% $90,000 (change order) $31,500 Mitigate: complete hardware audit before contract signature
R2 Points API design changes after POS integration has started 20% $60,000 (vendor rework under change order) $12,000 Mitigate: freeze API contract before POS kickoff
R3 Marketing launch date is publicly announced before platform completion is confirmed 15% $150,000 (reputational + forced discount to cover a broken promise) $22,500 Avoid: no public date until platform hits UAT sign-off

python3 -c "print(0.35*90000, 0.20*60000, 0.15*150000, 0.35*90000+0.20*60000+0.15*150000)"
→ $31,500 + $12,000 + $22,500 = $66,000 total program contingency reserve.

Step 4 — Vendor contract terms (POS integration)

Term Value
Contract type Fixed-price
Price $310,000
Milestone payments 30% on kickoff, 40% on integration test pass, 30% on go-live sign-off
SLA 99.5% uptime for POS-to-platform connection post go-live
Penalty clause 1% of contract value per week late, capped at 10%
Exit clause 30-day data transition assistance if terminated for cause

Fixed-price is the right call here specifically because R1's mitigation (a completed hardware audit before signature) removes the main source of scope ambiguity that would otherwise make fixed-price risky for the vendor to price accurately — and therefore risky for the buyer to receive change orders against.

Step 5 — Program-level EVM tracking (mid-point checkpoint, week 11)

At week 11, combined program figures: BAC = $850,000 (all three projects' budgets summed), PV = $520,000, EV = $460,000, AC = $505,000.

python3 -c "
BAC, PV, EV, AC = 850000, 520000, 460000, 505000
CPI = EV/AC
SPI = EV/PV
EAC_both = AC + (BAC - EV) / (CPI * SPI)
VAC = BAC - EAC_both
print(round(CPI,4), round(SPI,4), round(EAC_both,2), round(VAC,2))
"
Result: CPI = 0.9109, SPI = 0.8846, EAC (both) ≈ $988,998, VAC ≈ −$138,998.

Both indices sit in Red/Amber-border territory (module 09's thresholds): a projected $138,998 overrun on an $850,000 program at only the midpoint is enough to trigger a program-level review, not just a note in the status report — consistent with the recovery-readiness signals from module 08.

Step 6 — Program status rollup (PMO-style dashboard)

Project CPI SPI RAG Note
Loyalty platform build 0.93 0.90 Amber Slight schedule slip, being monitored
POS integration 0.88 0.85 Red Vendor flagged hardware audit findings adding scope — R1 materialising
Marketing launch Not started Not started Green (on plan, not yet due)

R1 (probability 35%, EMV $31,500) is the risk that appears to be materialising here — the vendor's hardware audit findings driving POS integration's Red status. The program manager's next action is drawing down the $66,000 reserve for the actual change-order cost once quantified, and re-forecasting the program EAC with the updated POS project numbers.

How It Actually Works

The week-11 checkpoint numbers here show the multiplicative-uncertainty mechanic from Module 1 concretely: the POS integration project's Red status (SPI 0.85, CPI 0.88) isn't just that one project's problem — because the Loyalty platform and Marketing launch projects sit on a dependency seam downstream of shared program infrastructure, the compounded probability of the program hitting its combined date is the product of each project's conditional on-time probability, not their average, exactly as in Module 1's worked example. The reserve drawdown decision applied here also follows the EMV-drift diagnostic from Module 3 — R1 materializing at a moment when the register had estimated only a 35% chance means the register's probability estimate for this risk category should be revised upward for any remaining similar risks in the program, not treated as an isolated unlucky draw, because a vendor audit finding scope gaps is frequently a systemic signal about that vendor's other in-flight deliverables, not a one-off.

Stretch goals

  • Extend the risk register with a fourth risk that spans two of the three projects (a genuine program-level risk, not one that belongs to a single project's own register) and calculate its EMV.
  • Rebuild the week-11 EVM rollup assuming POS integration's change order actually costs $45,000 more than R1's estimated impact — recompute program EAC and VAC with python3 -c and state the new reserve balance.
  • Draft the stage-gate criteria (module 05) this program would need to pass at a G3 mid-point gate, using the actual week-11 numbers above to decide whether it would pass or be sent back for a recovery plan.