02 · Portfolio Management Basics

A portfolio is the full set of projects and programs an organisation is funding at once — often unrelated to each other, competing for the same pool of money and people. Portfolio management answers one question the project or program level cannot: given limited capacity, which of these should we be doing at all? Get this wrong and your best project managers deliver flawless projects that nobody should have funded.

Portfolio vs. program vs. project (recap)

Project Program Portfolio
Question answered How do we deliver this? How do these related things add up to a benefit? Which things should we fund?
Scope Fixed Related set Organisation-wide, may be unrelated
Owner Project manager Program manager Portfolio manager / PMO / executive committee

A scoring model for prioritisation

Comparing a compliance project to a growth project to a cost-cutting project on "which is more important" is a values argument dressed up as analysis unless you have a shared scoring model. A simple weighted model:

Criterion Weight What it measures
Strategic alignment 30% Does this map to a named strategic objective this year?
Financial value (NPV/ROI band) 25% Expected return relative to cost
Risk (inverted — lower risk scores higher) 15% Likelihood of failure or major overrun
Urgency / cost of delay 15% What happens if we wait a year?
Resource feasibility 15% Can we actually staff it without gutting something else?

Each criterion is scored 1–5 by a review board, weighted, and summed to a 100-point scale.

Worked example: scoring four candidate projects

Project Alignment (30%) Value (25%) Risk (15%, inverted) Urgency (15%) Feasibility (15%)
A: Core platform migration 5 3 2 3 3
B: New mobile app 3 5 3 4 4
C: Regulatory compliance update 5 2 5 5 5
D: Internal tooling refresh 2 3 4 2 5

Weighted score = Σ(criterion score × weight) × 20 (to put on a 100 scale since raw scores are out of 5):

A = (5*0.30 + 3*0.25 + 2*0.15 + 3*0.15 + 3*0.15) * 20
B = (3*0.30 + 5*0.25 + 3*0.15 + 4*0.15 + 4*0.15) * 20
C = (5*0.30 + 2*0.25 + 5*0.15 + 5*0.15 + 5*0.15) * 20
D = (2*0.30 + 3*0.25 + 4*0.15 + 2*0.15 + 5*0.15) * 20

Verified with python3:

Project Weighted score
A 69.0
B 76.0
C 85.0
D 60.0

C (compliance) clearly outranks the others despite lower financial value, because its risk, urgency, and feasibility scores are high — this is the model correctly capturing that a compliance deadline with heavy non-compliance penalties outranks a nice-to-have growth bet, even though a value-only ranking would have put B first.

The balance: not just the top-N by score

Ranking alone produces a portfolio that's all one type of bet. A mature portfolio review balances the ranked list against a target mix:

Category Target % of budget Current % Gap
Run-the-business (keep-the-lights-on) 40% 55% Over by 15pts
Grow-the-business (new revenue) 35% 20% Under by 15pts
Transform-the-business (strategic bets) 25% 25% On target

A portfolio 55% run-the-business is starving growth even if every individual score is defensible — the review board's job is to notice the mix problem the scoring model alone won't surface, and deliberately fund a lower-scoring growth project over a higher-scoring maintenance one to correct the balance.

Capacity-constrained selection

With a ranked list and a fixed budget, selection is a constrained optimisation, not just "fund the top of the list until money runs out" — that greedy approach can leave large amounts unspent or lock out a high-value project that needs a big-but-not-huge slice.

Project Score Cost ($k) Score per $k
C 85.0 300 0.283
B 76.0 900 0.084
A 69.0 600 0.115
D 60.0 150 0.400

With a $1,000k budget: funding by raw score (C, B) uses $1,200k — over budget, so B is dropped, leaving $700k unspent capacity idle. Funding by score-per-dollar instead (D, C, A) uses $1,050k — still slightly over. The actual decision a review board makes: fund D + C + A minus a $50k trim on A's scope, capturing three initiatives instead of two, and getting more total strategic value per dollar than chasing the single highest-scoring project.

Portfolio dashboard

Project Score Status Budget used Schedule Risk trend
A 69.0 Active 40% On track Stable
C 85.0 Active 15% On track Improving
D 60.0 Active 60% 2 weeks late Stable
B 76.0 Deferred to next cycle

How It Actually Works

Capacity-constrained selection is a version of the knapsack problem: you have a fixed capacity (budget, or full-time-equivalent headcount) and a set of candidate projects each with a "weight" (cost) and a "value" (strategic score), and the objective is to select the subset maximizing total value without exceeding capacity. Picking strictly top-N by score, the naive approach, is provably suboptimal against a hard capacity constraint — the correct heuristic is to rank by value density, score / cost, not raw score, because a lower-scoring but cheaper project can free capacity for two more projects than one expensive high-scorer would allow, producing more total value from the same budget. This is exactly analogous to Level 2 Module 5's FPIF share-ratio math and Module 2's cost-slope crashing decisions — all three are constrained-optimization problems where the naive "pick the biggest number" heuristic loses to "pick the best ratio" heuristic once a hard constraint is binding. True optimal knapsack selection is computationally expensive at scale (NP-hard), which is the actual technical reason portfolio tools use the value-density heuristic rather than solving for a global optimum — it's a fast, usually-near-optimal approximation, not a shortcut taken out of laziness.

Exercise

Score two new candidate projects using the weighted model above (alignment 30%, value 25%, risk 15% inverted, urgency 15%, feasibility 15%): Project E (alignment 4, value 4, risk 3, urgency 2, feasibility 4) and Project F (alignment 2, value 5, risk 1, urgency 5, feasibility 2).

  1. Compute each weighted score on the 100-point scale and verify your arithmetic with python3 -c.
  2. Given a portfolio already spending 55% on run-the-business against a 40% target, argue for or against funding whichever of E/F scores higher, using the category-mix table as part of your reasoning, not just the score.
  3. List one thing the scoring model in this module cannot tell you that a human review board still has to judge.