10 · Project — Agile Plan with Sprint Schedule

Everything in Level 2 has been taught one discipline at a time: sprints in one module, float in another, earned value in a third, risk and quality and reporting each in their own. Real projects do not arrive in that shape. They arrive as one delivery that has to be planned, sequenced, de-risked, quality-gated and reported on at the same time, from the same set of numbers.

This capstone builds a complete agile delivery plan for one project and then demands the thing that separates a plan from a document: internal consistency. The velocity in the sprint plan must produce the forecast in the dashboard. The contingency reserve must be sized by the risk register, not chosen. The defect data behind the quality gate must be the same data the dashboard reports. If you can change one number in one artefact and nothing else moves, the artefacts are not connected and the plan is decoration.

The worked project

Attribute Value
Project MemberHub — customer self-service portal (replaces phone-only servicing)
Sponsor Director of Customer Operations
Delivery model Scrum, 2-week sprints, 5 sprints planned (10 weeks / 50 working days)
Team 6 people: PO, Scrum Master, 3 developers, 1 tester
Backlog at baseline 200 story points, estimated by planning poker
Cost baseline (BAC) $200,000 — a flat team burn of $40,000 per sprint
Derived rate $200,000 ÷ 200 points = $1,000 per story point
Contingency reserve $52,000 (sized in the risk register below)
Management reserve $20,000, sponsor-controlled
Total funding envelope $272,000

The $1,000-per-point rate is what makes agile delivery legible to earned value. Points are the measure of work; the rate converts accepted points into earned value without inventing a second tracking system.


Artefact 1 — the release and sprint plan

Sprint Dates (working days) Sprint goal Planned points Cumulative planned
1 1–10 Login, account view, audit logging 40 40
2 11–20 Payment history, statement download 40 80
3 21–30 Update payment method, address change 40 120
4 31–40 Claims submission, document upload 40 160
5 41–50 Notifications, accessibility fixes, hardening 40 200

The plan assumes a baseline velocity of 40 points per sprint. That is a forecast, not a commitment — the only honest thing to do with it is to replace it with measured velocity as soon as three sprints of real data exist, which is exactly what happens below.

Sprint backlog template

One sprint is planned in detail; the rest are goals only. Planning all five sprints to task level would be four sprints of waste.

Story ID Story Points Acceptance criteria Owner Status
MH-104 As a member I can view my payment history for 24 months 8 24 months returned; paginated at 12; empty state handled Dev A Done
MH-105 As a member I can download a statement as PDF 5 PDF matches the on-screen figures; generated < 3 s Dev B Done
MH-109 As a member I can filter payments by date range 3 Invalid ranges rejected with a message; defaults to 12 months Dev A In test
MH-112 As an agent I can see what a member saw, for support calls 8 Read-only; access written to the audit log Dev C In progress

Velocity and the forecast it produces

After three sprints there is real data, and it does not match the plan.

Sprint Committed Accepted Variance Note
1 40 36 −4 Environment access lost 2 days
2 40 41 +1 Recovered one carried story
3 40 35 −5 Two developers pulled to a production incident
  • Total accepted after 3 sprints = 36 + 41 + 35 = 112 points
  • Measured average velocity = 112 ÷ 3 = 37.3 points per sprint
  • Backlog remaining = 200 − 112 = 88 points
  • Sprints still required = 88 ÷ 37.3 = 2.36 sprints
  • Total forecast = 3 + 2.36 = 5.36 sprints against a 5-sprint plan

The forecast overruns by 0.36 of a sprint — about 4 working days — but sprints are not divisible, so in practice this is a sixth sprint or a scope reduction of roughly 14 points. Say that to the sponsor in those terms. "We are tracking slightly behind" is not a decision; "one more sprint at $40,000, or cut 14 points from Sprint 5" is.

Artefact 1b — the enabling track, critical path and float

Not everything in a delivery is a story. The enabling work — environments, contracts, security testing, cutover — is a dependency network and behaves like one. This track starts on day 11 (the start of Sprint 2) and gates a go-live review on day 50.

ID Activity Duration Predecessor ES EF LS LF Float
A Provision environments 5 0 5 0 5 0
B Identity / SSO integration 10 A 5 15 5 15 0
C Payment gateway contract + sandbox 12 A 5 17 11 23 6
D Data migration build 8 B 15 23 15 23 0
E Security penetration test 6 C, D 23 29 23 29 0
F Production cutover rehearsal 3 E 29 32 29 32 0

Days are counted from the start of the track. Reading the network:

  • Critical path = A → B → D → E → F, total 5 + 10 + 8 + 6 + 3 = 32 days.
  • Activity C has 6 days of free float: it can finish as late as day 23 without moving E, because D also feeds E and D does not finish until day 23.
  • The track starts on day 11, so cutover rehearsal completes on project day 11 + 32 = day 43, against a go-live gate on day 507 days of project-level slack.

Those 7 days are the entire buffer protecting go-live, and the velocity forecast above already wants 4 of them. The buffer is 3 days deep, not 7. Two independent artefacts are pointing at the same conclusion, which is what consistency looks like when it is working.


Artefact 2 — the risk register

Probability is a decimal, impact is a cost, and EMV = probability × impact. The register is sorted by EMV because that is the order in which attention is worth spending.

ID Risk (cause → event → effect) P Impact EMV Response Owner
R1 Because the gateway vendor certifies in monthly windows, certification may miss the window, delaying payment stories 0.40 $30,000 $12,000 Mitigate — book the window in Sprint 1, not Sprint 3 PM
R3 Because the portal is the first internet-facing service, pen testing may find severity-1 findings needing rework 0.50 $24,000 $12,000 Mitigate — threat-model in Sprint 2; pre-scan before formal test Security Lead
R2 Because one developer holds all legacy billing knowledge, their loss would stall integration 0.20 $45,000 $9,000 Mitigate — pair on all billing stories; document the interface Eng Manager
R5 Because sprint demos attract new stakeholders, scope may grow beyond the 200-point baseline 0.60 $15,000 $9,000 Mitigate — all demo requests enter the backlog, none enter the sprint PO
R4 Because legacy address data was never validated, migration quality may be worse than sampled 0.30 $20,000 $6,000 Mitigate — profile 100% of records in Sprint 2, not a sample Data Lead
R6 Because load profiles are estimated, the portal may fail the 2-second SLA at peak 0.25 $16,000 $4,000 Mitigate — load test from Sprint 3, not at the end Tech Lead
Total expected monetary value $52,000

The contingency reserve is $52,000 because the register says $52,000 — not because someone applied 25% to the budget and it felt about right. When a risk closes, its EMV is released from the reserve and the number moves. A reserve that never changes is not being managed.


Artefact 3 — the quality plan

Definition of Done

A story is not done until every line is true. This is a gate, not a preference — one unchecked line means the story is not accepted and its points are not earned.

# Criterion Evidence
1 Acceptance criteria demonstrated by the tester, not the developer Test run recorded against the story
2 Peer review complete, comments resolved Approved review on the change
3 Unit and integration tests pass in CI Green pipeline on the merge commit
4 No new severity-1 or severity-2 defects Defect tracker query attached
5 Accessibility checked (keyboard, contrast, labels) Checklist per screen
6 Response time within SLA under the standard load profile Load test result
7 Audit logging present for any data change Log sample
8 User-facing text reviewed by Customer Operations Sign-off in the story

Release readiness checklist (go-live gate, day 50)

Gate Threshold Status at Sprint 3
Severity-1 defects open 0 2 — not met
Severity-2 defects open ≤ 3 5 — not met
Pen test findings closed 100% of high Test not yet run (day 29 of track)
Data migration accuracy ≥ 99.5% on full run 97.8% on profile run — not met
Rollback rehearsed Once, end to end Scheduled day 32
Support team trained 100% of tier-1 agents 0% — starts Sprint 4

Pareto analysis of defect causes

200 defects have been raised across the first three sprints. Sorted by frequency:

Cause Defects % of total Cumulative %
Ambiguous acceptance criteria 76 38.0% 38.0%
Test data not representative of production 48 24.0% 62.0%
Third-party API behaviour changed 30 15.0% 77.0%
Browser / device compatibility 20 10.0% 87.0%
Performance under load 14 7.0% 94.0%
Copy and content errors 8 4.0% 98.0%
Other 4 2.0% 100.0%
Total 200 100%

Three causes out of seven produce 154 of 200 defects — 77%. The action that follows is not "improve quality"; it is to fix acceptance-criteria writing and test data, because those two alone account for 62%. Note the loop back to Artefact 1: ambiguous acceptance criteria is a refinement failure, so the fix lives in the sprint process, not in the test phase.


Artefact 4 — the reporting dashboard

Earned value at the end of Sprint 3

Points convert to money at $1,000 per point, so the EVM inputs fall straight out of the velocity table.

Input Derivation Value
BAC 200 points × $1,000 $200,000
PV 120 points planned × $1,000 $120,000
EV 112 points accepted × $1,000 $112,000
AC Actuals from timesheets and contractor invoices $128,000
Metric Formula Calculation Result
Cost Variance EV − AC 112,000 − 128,000 −$16,000
Schedule Variance EV − PV 112,000 − 120,000 −$8,000
CPI EV ÷ AC 112,000 ÷ 128,000 0.875
SPI EV ÷ PV 112,000 ÷ 120,000 0.933
EAC BAC ÷ CPI 200,000 ÷ 0.875 $228,571
ETC EAC − AC 228,571 − 128,000 $100,571
VAC BAC − EAC 200,000 − 228,571 −$28,571
TCPI (to BAC) (BAC − EV) ÷ (BAC − AC) 88,000 ÷ 72,000 1.222

Read the three ratios in order: planned 60% complete (PV ÷ BAC), actually 56% complete (EV ÷ BAC), spent 64% (AC ÷ BAC). Behind and overspent, both mildly, both in the same direction.

Two cross-checks confirm the artefacts agree:

  • SPI 0.933 implies a duration of 5 ÷ 0.933 = 5.36 sprints — the exact figure the velocity forecast produced independently.
  • The VAC of $28,571 consumes 28,571 ÷ 52,000 = 55% of the contingency reserve, which by the risk-exposure threshold below is amber, not red.

TCPI 1.222 is the number to argue about. It says every remaining dollar must buy 22% more work than every dollar so far has bought. Nothing in the velocity data suggests the team is about to become 22% more efficient. Report EAC $228,571 as the forecast, and treat "we'll recover it" as a claim requiring evidence.

The one-page sprint dashboard

Panel Value at Sprint 3 Rule Status
Overall Behind, overspent, quality gates failing See below Red
Schedule SPI 0.933; forecast 5.36 sprints vs 5 planned Amber 0.90–0.94 Amber
Cost CPI 0.875; EAC $228,571; VAC −$28,571 Red < 0.90 Red
Scope 112 of 200 points accepted (56%); 0 changes approved Green
Quality 2 severity-1 open; migration accuracy 97.8% vs 99.5% Red ≥ 3 sev-1 Amber
Risk Reserve consumed 55% ($28,571 of $52,000) Amber 60–90% Green
Float Enabling track has 7 days; forecast wants 4 < 5 days spare = amber Amber
Decision needed Approve Sprint 6 ($40,000) or cut 14 points by day 30 Open

Overall is Red on the CPI rule, and stays red however uncomfortable the conversation is. The decision panel is what makes the report worth sending: it names two options, prices both, and gives the date beyond which the choice is made by default.

How It Actually Works

This worked plan's hybrid model exposes exactly why the earned-value figures and the sprint velocity figures must be reconciled through one shared unit of work, not tracked as two separate systems: PV/EV are stated in dollars against a time-phased baseline, while velocity is stated in story points against a sprint cadence, and translating between them requires a stable $/point conversion — Planned $/sprint = (points planned that sprint / total points) × total budget. If a sprint's velocity underperforms, that shows up as an SPI < 1 in EVM terms without any separate calculation, but only if the $/point rate used to convert them was itself derived from a representative sprint — deriving it from an anomalously fast early sprint (before the team's true velocity stabilized around its statistical mean, per Module 1's variance discussion) silently understates the $/point rate and makes every later sprint look artificially over budget on the dashboard even when nothing has actually changed about team performance.

Exercise

Build the same four connected artefacts for a project of your own — reuse the backlog, risk register or dashboard you produced in this level's earlier exercises if they fit, or start fresh.

  1. Sprint plan. Define a backlog in points, a baseline velocity, a sprint count and a cost baseline. Derive your cost-per-point and state it explicitly. Plan one sprint to story level with acceptance criteria; plan the rest to goal level only.
  2. Velocity forecast. Invent (or use real) accepted points for the first three sprints. Compute measured velocity, remaining backlog, sprints required and total forecast sprints. Convert the overrun into either a cost or a scope reduction, in numbers.
  3. Enabling track. Build a network of at least six non-story activities with dependencies. Do the forward and backward pass, identify the critical path, and find at least one activity with float. State how much project slack protects go-live and how much of it the velocity forecast consumes.
  4. Risk register. At least six risks in cause → event → effect form, each with probability, cost impact, EMV and a named owner. Total the EMV and set your contingency reserve to that total.
  5. Quality plan. Write a Definition of Done of at least eight checkable lines with evidence for each, a release-readiness gate with thresholds, and a Pareto table of defect causes whose percentages sum to 100%. State which few causes give you the majority of the defects, and what you will change because of it.
  6. Dashboard. Compute CV, SV, CPI, SPI, EAC, ETC, VAC and TCPI from your own points and actuals. Then prove consistency two ways: show that sprints ÷ SPI matches your velocity forecast, and that your VAC as a percentage of the contingency reserve matches your risk panel.
  7. The consistency test. Change your Sprint 3 accepted points by ±5 and list every number across all four artefacts that must move. If fewer than six numbers move, your artefacts are not yet connected — find the disconnection and fix it.

Stretch goals

  • Re-baseline properly. Sprint 6 is approved. Produce the revised baseline: new BAC, new sprint plan, and the change record explaining what was approved, by whom and on what date. Then compute EVM against the new baseline and against the original one, and explain to a sponsor why the second number still matters.
  • Model the risk instead of averaging it. Take your six risks and run a simple three-point analysis on total exposure: best case (no risk occurs), expected case (EMV total), worst case (all risks occur). Compare the worst case against your contingency reserve and state what you would tell the sponsor about reserve adequacy.
  • Add a leading indicator. Choose one metric that would have predicted the Sprint 3 velocity drop before it happened — unplanned work as a percentage of capacity is a good candidate. Backfill it for three sprints and show whether it moved first.
  • Kill a story. Identify the 14 points you would cut instead of funding Sprint 6, justify each cut against the sponsor's original business objective, and write the two-paragraph recommendation you would actually send.