10 · Project — Full Project Charter & Schedule

This capstone project pulls together every framework from Level 1 into one coherent deliverable for a single sample project: a project charter, scope statement, WBS, schedule with critical path, budget, risk register, and stakeholder/communication plan. Read through the worked example below — it's a complete, realistic deliverable — then produce your own version for a project of your choosing in the Exercise.

The sample project: "Launch a Customer Referral Program"

A mid-size subscription software company (120 employees) wants to launch a customer referral program: existing customers get a discount for referring new customers, tracked through a small web portal integrated with the existing billing system. Below is the full set of Level 1 deliverables for this project.

1. Project Charter

Element Content
Purpose Increase new customer acquisition through existing customer referrals, at lower cost-per-acquisition than paid marketing
Objectives Launch a functioning referral portal within 10 weeks; achieve at least 50 completed referrals in the first quarter post-launch
Sponsor VP of Marketing
Key stakeholders Marketing, Engineering, Billing/Finance, Customer Support
High-level budget $45,000
High-level timeline 10 weeks
Assumptions Existing billing system has an API the portal can integrate with
Constraints Must not require any change to the core billing system's data model
Assigned PM [You]

2. Scope Statement

  • Deliverables: (1) referral portal (customer-facing page to generate and share a referral link), (2) billing integration (apply discount automatically when a referred customer subscribes), (3) admin dashboard (Marketing can see referral counts and program performance).
  • Acceptance criteria: a customer can generate a unique referral link, a new customer signing up via that link triggers an automatic discount for both parties, and Marketing can view real-time referral counts in the dashboard.
  • Exclusions: no changes to the core billing data model (per the charter's constraint); no mobile app version (web only, this phase); no multi-tier/multi-level referral rewards (single-level only, this phase).
  • Constraints: fixed $45,000 budget; must not touch the billing data model; must launch before the start of Marketing's Q3 campaign push.
  • Assumptions: the existing billing system's API supports applying a discount code programmatically without a data-model change.

3. Work Breakdown Structure

WBS ID Deliverable / Work package
1.1 Design — referral portal UX
1.2 Design — admin dashboard UX
2.1 Development — referral link generation
2.2 Development — billing API integration
2.3 Development — admin dashboard
3.1 Testing — end-to-end referral flow
3.2 Testing — dashboard accuracy
4.1 Launch — soft launch to 10% of customers
4.2 Launch — full rollout

4. Schedule and Critical Path

Task Duration Depends on
1.1 Portal design 1 week
1.2 Dashboard design 1 week
2.1 Link generation dev 2 weeks 1.1
2.2 Billing integration dev 3 weeks 1.1
2.3 Dashboard dev 2 weeks 1.2
3.1 End-to-end testing 1 week 2.1, 2.2
3.2 Dashboard testing 1 week 2.3
4.1 Soft launch 1 week 3.1, 3.2
4.2 Full rollout 1 week 4.1

Tracing the paths: 1.1 → 2.2 → 3.1 → 4.1 → 4.2 = 1+3+1+1+1 = 7 weeks is the longest path (the billing integration, at 3 weeks, is the single longest task and sits on the critical path). The path through the dashboard (1.2 → 2.3 → 3.2 → 4.1 → 4.2 = 1+2+1+1+1 = 6 weeks) has 1 week of float — meaning dashboard work could slip by up to a week without affecting the overall 7-week finish, but the billing integration cannot slip at all without pushing the launch date.

5. Budget

Item Cost
Design (portal + dashboard) $6,000
Development (link gen + billing integration + dashboard) $26,000
Testing $4,000
Launch (soft + full rollout support) $3,000
Subtotal $39,000
Contingency (sized from risk register below: $2,400 + $1,600 + $1,000 ≈ $5,000, rounded) $5,000
Wait — check against charter budget $44,000 ≤ $45,000 ✓

6. Risk Register

Risk Probability Impact Priority Response
Because the billing API has never been used for real-time discount application, integration may take longer than the 3-week estimate Medium High High Mitigate — run a 2-day technical spike in week 1 to validate the API can do this before committing the full 3-week estimate
Because Customer Support hasn't been consulted on the referral flow, they may be unprepared for related support tickets at launch Medium Medium Medium Mitigate — include Support in the soft-launch review before full rollout
Because this is the team's first referral program, the discount abuse potential (e.g., self-referral) may not be fully covered by initial design Low High Medium Mitigate — explicit design review step for abuse cases before dev sign-off

7. Stakeholder & Communication Plan

Stakeholder Power Interest Engagement Format/Frequency
VP of Marketing (sponsor) High High Manage closely Weekly 1:1
Engineering lead High High Manage closely Daily stand-up + weekly 1:1 with PM
Billing/Finance High Medium Involve early, brief at checkpoints Written brief at design sign-off and pre-launch
Customer Support Low High Keep informed, gather input Bi-weekly demo, included in soft-launch review
Executive leadership High Low Keep satisfied Single summary at kickoff and at full rollout

How It Actually Works

Pulling the referral-program deliverables together exposes a mechanic that's invisible when each artifact is studied alone: the schedule baseline and cost baseline are the same underlying data, viewed through two different lenses. Each task in the network carries both a duration and a resource cost-per-day; summing durations along the critical path gives the project end date, while summing (duration × daily burn rate) across all tasks — critical and non-critical alike — gives the budget. This is why a change that only affects a non-critical task (say, adding scope to the low-float "training material" task) can leave the finish date untouched while still moving the budget, and conversely why crashing the critical path (Level 2) moves the finish date while adding cost without touching total scope. The risk register's EMV entries should sum into the very same budget as a contingency reserve line — not as buffer stated separately from "the real budget," because on a fully-integrated baseline the approved budget is base cost plus contingency reserve, and only management reserve sits outside the PM's baseline authority. A charter that doesn't wire these three numbers together (schedule total, cost baseline, EMV-derived reserve) into one consistent model isn't actually integrated — it's three separate documents that happen to describe the same project.

Exercise

Produce your own complete Level 1 capstone for a project of your choice — reuse and refine the scope statement, risk register, and stakeholder register you built in this level's earlier module exercises if they fit, or start fresh with a new project idea. Your deliverable must include all seven sections shown above: charter, scope statement, WBS, schedule with an explicitly calculated critical path (show the path calculations, not just the final answer), budget (with contingency tied to specific risks, not a flat percentage), risk register, and stakeholder/communication plan. Keep it realistic and internally consistent — the budget should reflect the WBS, the schedule should reflect the WBS, and the risk register's contingency sizing should trace back to specific line items in the risk register, the way the worked example above does.